Ohio Rev. Code § 4906.212: Decommissioning estimated costs recalculation.
Where this section sits in the code
- Title 49 Public Utilities
- Chapter 4906 Power Siting
The estimate of the total decommissioning costs of a utility facility, as described in division (B)(3) of section 4906.211 of the Revised Code, shall be recalculated every five years by an engineer retained by the applicant.