Ohio Rev. Code § 4926.48: Burden of proof regarding rate, term, or condition or denial of access.

Read at publisher ↗
Where this section sits in the code
  1. Title 49 Public Utilities
  2. Chapter 4926 Electric Cooperative Pole Attachments

(A) The complainant under section 4926.39 of the Revised Code has the burden of establishing a prima facie case that the rate, term, or condition complained of is not just and reasonable or that the denial of access was unlawful.

(B) In a case involving a denial of access, the electric cooperative has the burden of establishing, by a preponderance of the evidence, that the denial was lawful, once a prima facie case is established by the complainant.