Okla. Stat. tit. 61, § 61-224: Payment of subcontractor or sub-contractor or supplier -

Read at publisher ↗
Where this section sits in the code
  1. OK Code
  2. Title 61

Time limit.

A. If a subcontractor or material supplier has performed in

accordance with the provisions of a construction contract, the prime

contractor shall make payment to the subcontractor or material

supplier no later than ten (10) calendar days after the prime

contractor receives its corresponding payment for the work

performed.

B. If a sub-subcontractor or material supplier has performed in

accordance with the provisions of a construction contract, the sub-

subcontractor or material supplier shall be entitled to receive

payment no later than seven (7) calendar days after subcontractor

receives its corresponding payment for the work performed.