GroundRules
← Search the law
Oregon · Through 2025 Edition

ORS 279C.660: Compensation when contract terminated due to public interest.

Read at publisher ↗
Where this section sits in the code
  1. 07 - Public Facilities and Finance
  2. 26. Public Facilities, Contracting and insurance
  3. Chapter 279C — Public Contracting - Public Improvements and Related Contracts

When a public contract is terminated by mutual agreement, provision shall be made for the payment of compensation to the contractor. In addition to a reasonable amount of compensation for preparatory work and for all costs and expenses arising out of termination, the amount to be paid to the contractor:

      (1) Shall be determined on the basis of the contract price in the case of any fully completed separate item or portion of the work for which there is a separate or unit contract price; and

      (2) May, with respect to any other work, be a percent of the contract price equal to the percentage of the work completed.

Collected 2026-09-03T23:50:13Z. Source file · JSON

Browse this collection