ORS 279C.655: Extension and compensation when work suspended.
Where this section sits in the code
- 07 - Public Facilities and Finance
- 26. Public Facilities, Contracting and insurance
- Chapter 279C — Public Contracting - Public Improvements and Related Contracts
If a public contract is not terminated but work under the contract is suspended by an order of a contracting agency for any reason considered to be in the public interest other than a labor dispute or any third-party judicial proceeding relating to the work other than a suit or action filed in regards to a labor dispute, the contractor is entitled to a reasonable extension of the contract time and reasonable compensation for all costs resulting from the suspension plus a reasonable allowance for overhead with respect to such costs.