SDCL § 46-4-6: Time for construction and completion of dam.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 46. WATER RIGHTS
  2. CHAPTER 46-4. DRY-DRAW AND NONNAVIGABLE STREAM DAMS

Any person appropriating the waters of any dry-draw or watercourse within this state, within sixty days after the filing of the notice provided for in §§ 46-4-3 and 46-4-4, shall begin the construction of the dam mentioned in § 46-4-1 for the storage or diversion of the waters, shall proceed diligently to complete the dam and shall divert the waters for beneficial use as rapidly as possible.