Tex. Transportation Code § 373.057: PROGRESS REPORTS.
Where this section sits in the code
- TRANSPORTATION CODE
- TITLE 6. ROADWAYS
- SUBTITLE G. TURNPIKES AND TOLL PROJECTS
- CHAPTER 373. TOLL PROJECTS LOCATED IN TERRITORY OF LOCAL TOLL PROJECT ENTITY
- SUBCHAPTER B. PROCESS TO DETERMINE ENTITY TO DEVELOP, FINANCE, CONSTRUCT, AND OPERATE TOLL PROJECT
After the department or the local toll project entity exercises an option under this subchapter, the department or the local toll project entity, as applicable, shall issue a semiannual report on the progress of the development of the toll project. The report shall be made available to the public.
Added by Acts 2011, 82nd Leg., R.S., Ch. 1196 (S.B. 19), Sec. 1, eff. June 17, 2011.