6VAC15-81-420: Bids
Where this section sits in the code
- Title 6. Criminal Justice And Corrections
- Agency 15. State Board of Local and Regional Jails
- Chapter 81. Standards for Planning, Design, Construction, and Reimbursement of Local Correctional Facilities
- Part III. Project Development
- Article 3. Funding and Reimbursement
A. Prior experience with jail construction is an element to be considered when selecting a contractor.
B. After bids for construction have been received and opened, and the owner has determined to proceed with the project, the owner or owner's agent shall submit a copy of the bid tabulation to the reviewing authority.
C. For projects utilizing nontraditional process, other than design-bid-build, the schedule of values shall be submitted within 45 days after award of the construction contract.