18 CFR 1308.24: Undue delay in Contracting Officer's decision.

Read at publisher ↗
Where this section sits in the code
  1. Title 18—Conservation of Power and Water Resources
  2. CHAPTER XIII—TENNESSEE VALLEY AUTHORITY
  3. PART 1308—CONTRACT DISPUTES
  4. Subpart C—Board of Contract Appeals

(a) If there is an undue delay by a Contracting Officer in issuing a decision on a claim, the Contractor may request the Chairman to direct the Contracting Officer to issue a decision within a specified period of time.

(b) A request under this section shall:

(1) Be in writing;

(2) State the date on which the claim was submitted to the Contracting Officer.

(3) State the date suggested for issuance of a decision by the Contracting Officer.

(c) TVA may reply to a motion under this section within 5 days after its receipt.

(d) The Chairman shall issue a written decision on the request. If granted, the decision shall specify the date by which the Contracting Officer's decision is to be rendered, and a copy shall be served on the Contracting Officer.