23 CFR 636.118: Is team switching allowed after contract award?
Where this section sits in the code
- Title 23—Highways
- CHAPTER I—FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
- SUBCHAPTER G—ENGINEERING AND TRAFFIC OPERATIONS
- PART 636—DESIGN-BUILD CONTRACTING
- Subpart A—General
Where the offeror's qualifications are a major factor in the selection of the successful design-builder, team member switching (adding or switching team members) is discouraged after contract award. However, the owner may use its discretion in reviewing team changes or team enhancement requests on a case-by-case basis. Specific project rules related to changes in team members or changes in personnel within teams should be explicitly stated by the STD in all project solicitations.
Collected 2026-08-27T02:24:50Z. Source file · JSON