30 CFR 285.632: What documents must I submit before I may construct and install facilities under my approved COP?

Read at publisher ↗
Where this section sits in the code
  1. Title 30—Mineral Resources
  2. CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
  3. SUBCHAPTER B—OFFSHORE
  4. PART 285—RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF
  5. Subpart F—Information Requirements

(a) You must submit to BSEE the documents listed in the following table:

Document: Requirements are found in:

(1) Facility Design Report § 285.701

(2) Fabrication and Installation Report § 285.702

(b) You must submit your safety management system, as required by § 285.810.

(c) These activities must fall within the scope of your approved COP. If they do not fall within the scope of your approved COP, you will be required to submit a revision to your COP, under 30 CFR 585.634, for BOEM approval before commencing the activity.