30 CFR 285.651: When may I construct complex or significant OCS facilities on my limited lease or any facilities on my project easement proposed under my GAP?
Where this section sits in the code
- Title 30—Mineral Resources
- CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER B—OFFSHORE
- PART 285—RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF
- Subpart F—Information Requirements
If you are applying for a project easement, or installing a facility or a combination of facilities on your limited lease deemed by BOEM to be complex or significant, as provided in 30 CFR 585.648(a)(1), you also must comply with the requirements of subpart G of this part and submit your safety management system description required by § 285.810 before construction may begin.