30 CFR 585.614: When may I begin conducting activities under my approved SAP?

Read at publisher ↗
Where this section sits in the code
  1. Title 30—Mineral Resources
  2. CHAPTER V—BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR
  3. SUBCHAPTER B—OFFSHORE
  4. PART 585—RENEWABLE ENERGY ON THE OUTER CONTINENTAL SHELF
  5. Subpart G—Plans and Information Requirements

(a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.

(b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in § 585.613(a)(1), you must comply with the requirements of 30 CFR part 285, subpart G, and also submit your Safety Management System description required by 30 CFR 285.810 before construction may begin.