40 CFR 62.14630a: a By what date must I conduct the initial performance test?
Where this section sits in the code
- Title 40—Protection of Environment
- CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
- SUBCHAPTER C—AIR PROGRAMS
- PART 62—APPROVAL AND PROMULGATION OF STATE PLANS FOR DESIGNATED FACILITIES AND POLLUTANTS
- Subpart IIIa—Federal Plan Requirements for Commercial and Industrial Solid Waste Incineration Units That Commenced Construction On or Before June 4, 2010, and Have Not Been Modified or Reconstructed Since August 7, 2013
(a) The initial performance test must be conducted no later than 180 days after your final compliance date. Your final compliance date is January 10, 2025, or the date you restart your CISWI if later than January 10, 2025.
(b) If you commence or recommence combusting a solid waste at an existing combustion unit at any commercial or industrial facility and you conducted a test consistent with the provisions of this subpart while combusting the given solid waste within the 6 months preceding the reintroduction of that solid waste in the combustion chamber, you do not need to retest until 6 months from the date you reintroduce that solid waste.
(c) If you commence or recommence combusting a solid waste at an existing combustion unit at any commercial or industrial facility and you have not conducted a performance test consistent with the provisions of this subpart while combusting the given solid waste within the 6 months preceding the reintroduction of that solid waste in the combustion chamber, you must conduct a performance test within 60 days from the date you reintroduce solid waste.