40 CFR 62.14635a: a By what date must I conduct the initial air pollution control device inspection?
Where this section sits in the code
- Title 40—Protection of Environment
- CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
- SUBCHAPTER C—AIR PROGRAMS
- PART 62—APPROVAL AND PROMULGATION OF STATE PLANS FOR DESIGNATED FACILITIES AND POLLUTANTS
- Subpart IIIa—Federal Plan Requirements for Commercial and Industrial Solid Waste Incineration Units That Commenced Construction On or Before June 4, 2010, and Have Not Been Modified or Reconstructed Since August 7, 2013
(a) The initial air pollution control device inspection must be conducted within 60 days after installation of the control device and the associated CISWI reaches the charge rate at which it will operate, but no later than 180 days after January 10, 2025.
(b) Within 10 operating days following an air pollution control device inspection, all necessary repairs must be completed unless the owner or operator obtains written approval from the state agency establishing a date whereby all necessary repairs of the designated facility must be completed.