40 CFR 65.82: Design requirements.
Where this section sits in the code
- Title 40—Protection of Environment
- CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
- SUBCHAPTER C—AIR PROGRAMS
- PART 65—CONSOLIDATED FEDERAL AIR RULE
- Subpart E—Transfer Racks
(a) The owner or operator shall equip each transfer rack with either one of the following equipment:
(1) A closed vent system which routes the regulated material vapors to a control device as provided in § 65.83(a)(1) and (2).
(2) Process piping which routes the regulated material vapors to a process or a fuel gas system as provided in § 65.83(a)(4), or to a vapor balance system as provided in § 65.83(a)(3).
(b) Each closed vent system shall be designed to collect the regulated material displaced from tank trucks or railcars during loading and to route the collected regulated material to a control device as provided in § 65.83(a)(1) and (2).
(c) Process piping shall be designed to collect the regulated material displaced from tank trucks or railcars during loading and to route the collected regulated material vapors to a process or a fuel gas system as provided in § 65.83(a)(4), or to a vapor balance system as provided in § 65.83(a)(3).
(d) Each closed vent system shall meet the applicable requirements of § 65.143.
(e) If the collected regulated material vapors are routed to a process or a fuel gas system as provided in § 65.83(a)(4), then each owner or operator shall meet the applicable requirements of § 65.142(c).
Collected 2026-08-27T02:26:04Z. Source file · JSON