43 CFR 3179.43: Data submission and notification requirements.
Where this section sits in the code
- Title 43—Public Lands: Interior
- Subtitle B—Regulations Relating to Public Lands
- CHAPTER II—BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER C—MINERALS MANAGEMENT (3000)
- PART 3170—ONSHORE OIL AND GAS PRODUCTION
- Subpart 3179—Waste Prevention and Resource Conservation
(a) Table 1 is a summary of the Sundry Notice requirements in this subpart.
Table 1 to Paragraph (a)—Notification Via Sundry Notice Requirements
Sundry notice requirements Reference
Flaring of gas following removal of ≥50 percent of the natural gas liquids from the gas stream on-lease § 3179.41(b)(12).
Other gas sample location for flare approved by the AO § 3179.71(d)(3) and (e)(2).
Unavoidable/avoidable determination of loss of oil and/or gas while drilling for loss of well control event § 3179.80.
Extension of time limit or volumetric limit for well completion or recompletion flaring, or exploratory coalbed methane dewatering flaring § 3179.81(e).
Extension of time limit for well testing subsequent to initial completion § 3179.82.
Within 45 days of start of an emergency, estimate the volume flared or vented beyond the first 48 hours of the emergency § 3179.83(c).
Delay of leak repair beyond 30 calendar days with good cause § 3179.101(b).
(b) Table 2 summarizes the locations in this subpart that require an operator to provide information to the authorized officer upon request.
Table 2 to Paragraph (b)—Information Required at the Request of the AO
Information required at the request of the AO Reference
Ultrasonic meter flare gas testing report § 3179.71(c)(2)(i).
Ultrasonic meter manufacturer's specifications including installation and operation specifications § 3179.71(c)(2)(ii).
Recordkeeping for vented or flared gas events § 3179.72(c).
Recordkeeping for leak detection and repair § 3179.102(a).
(c) Table 3 summarizes the initial LDAR program submission and subsequent annual reporting.
Table 3 to Paragraph (c)—LDAR Program
Information required to be sent to the BLM State Office Reference
First submission of a leak detection and repair program to the BLM for review § 3179.100(b) and (d).
Annual review and update of the leak detection and repair program to the BLM § 3179.100(e).
Collected 2026-08-27T02:26:15Z. Source file · JSON