48 CFR 9.106-2: 9.106-2 Requests for preaward surveys.
Where this section sits in the code
- Title 48—Federal Acquisition Regulations System
- CHAPTER 1—FEDERAL ACQUISITION REGULATION
- SUBCHAPTER B—ACQUISITION PLANNING
- PART 9—CONTRACTOR QUALIFICATIONS
- Subpart 9.1—Responsible Prospective Contractors
The contracting officer's request to the surveying activity (Preaward Survey of Prospective Contractor (General), SF 1403) shall—
(a) Identify additional factors about which information is needed;
(b) Include the complete solicitation package (unless it has previously been furnished), and any information indicating prior unsatisfactory performance by the prospective contractor;
(c) State whether the contracting office will participate in the survey;
(d) Specify the date by which the report is required. This date should be consistent with the scope of the survey requested and normally shall allow at least 7 working days to conduct the survey; and
(e) When appropriate, limit the scope of the survey.